REAL TIME PERFORMANCE & MONITORING TOOL BASED DASH BOARDS FOR HOUSE SERVICE CONNECTION (Domestic Connection)


Particulars Details
Time Limit prescribed as per the Public Service Guatantee Act 21 days
Total Number of applications received 15384 nos
Total Number of connections completed 8788 nos
Average time taken to obtain connection 57.68 days
Median time taken to obtain connection 33 days
Minimum time taken to obtain connection 0 days
Maximum time taken to obtain connection 604 days


REAL TIME PERFORMANCE & MONITORING TOOL BASED DASH BOARDS FOR HOUSE SERVICE CONNECTION (Non Domestic Connection)


Particulars Details
Time Limit prescribed as per the Public Service Guatantee Act 21 days
Total Number of applications received 416 nos
Total Number of connections completed 208 nos
Average time taken to obtain connection 61.49 days
Median time taken to obtain connection 33 days
Minimum time taken to obtain connection 1 days
Maximum time taken to obtain connection 453 days

DYNAMIC DASHBOARDS FOR PERFORMANCE ANALYSIS AT VARIOUS LEVELS